The longest deepwater oil and gas pipeline in China has been laid and completed
AD |
Science and Technology Daily reporter Cao XiuyingOn June 22nd, in the Lingshui Sea area in the southeast of Hainan Island, with the termination of the closure and entry into the water, the key control project of the "Deep Sea No.1" ultra deep water atmospheric field phase II - the laying of the 20 inch submarine long-distance pipeline - was completed
Science and Technology Daily reporter Cao Xiuying
On June 22nd, in the Lingshui Sea area in the southeast of Hainan Island, with the termination of the closure and entry into the water, the key control project of the "Deep Sea No.1" ultra deep water atmospheric field phase II - the laying of the 20 inch submarine long-distance pipeline - was completed. This is the longest deepwater oil and gas pipeline in China, marking an important breakthrough in China's deepwater long-distance pipeline construction capacity and deepwater equipment technology.
The second phase of the "Deepsea No.1" project is approximately 130 kilometers away from Sanya, Hainan, and is located between the Yacheng 13-1 gas field and the "Deepsea No.1" energy station. The maximum operating water depth in the area is nearly 1000 meters, and the proven geological reserves of natural gas reach 50 billion cubic meters. After being put into operation, the peak annual production of the "Deepsea No.1" atmospheric field can be increased from 3 billion cubic meters to 4.5 billion cubic meters, becoming an important gas source to ensure China's energy security.
In order to efficiently and economically develop the second phase of "Deepwater No.1" project, CNOOC pioneered the oil and gas development mode of "underwater production system+shallow water jacket processing platform+deepwater Semi-submersible platform remote control system". On the one hand, a new oil and gas production and processing platform will be built in the shallow water area to connect with the Yacheng 13-1 gas field, and the oil and natural gas extracted from the second phase of the "Deep Sea No.1" project will be transported through a large-diameter subsea pipeline; On the other hand, the underwater production system of the "Deep Sea One" Phase II project is connected to the control system of the "Deep Sea One" energy station through a deep-sea umbilical cable, achieving remote control. Wu Hualin, Deputy Manager of the Deepwater Pipeline and Cable Department of the "Deep Sea No.1" Phase II Project of CNOOC Hainan Branch, introduced.
Submarine pipelines are the lifeline for ensuring the smooth transportation of offshore oil and gas. The second phase of the "Deep Sea No.1" project is China's first deepwater high-pressure gas field. The oil and gas extracted from the formation have complex composition, high temperature, and high pressure, and conventional materials of submarine pipes cannot meet production needs. China National Offshore Oil Corporation (CNOOC) has for the first time applied the combination plan of "114 kilometers of deepwater large-diameter seamless steel pipes+1.5 kilometers of deepwater bimetallic composite pipes" in a deepwater environment, building the "aorta" connecting the oil and gas transportation of the "Deepsea No.1" Phase II project.
This submarine pipeline is specially designed for the "mixed transportation of high-temperature, high-pressure, and strongly corrosive oil and gas". The pipeline design pressure can reach 38.8 MPa, and can transport oil and gas at a high temperature of 120 degrees Celsius. The maximum wall thickness reaches 38 millimeters, setting a new record for the wall thickness of offshore pipelines in China. Hou Jing, the chief engineer of the Phase II project of the "Deep Sea No.1" project, introduced: "We have collaborated with domestic manufacturers to optimize chemical composition, adopt high-precision rolling technology and advanced heat treatment technology, meet the requirements of high strength and high toughness indicators, achieve the full process of domestic production in research and development, and provide strong support for China's ultra deep water oil and gas development equipment
As the water depth increases, the difficulty of constructing submarine pipeline projects increases exponentially. The second phase of the "Deep Sea No.1" project is located in a sea area with complex geological conditions, including various complex terrains such as submarine steep slopes and large-scale sand slopes and ridges. It is the largest underwater pipeline in China with the largest water depth span, posing great challenges to engineering design, ship equipment capabilities, and offshore installation technology.
According to Guo Qing, the general contracting project manager of the "Deep Sea No.1" Phase II project of CNOOC Engineering, the project team has conducted extensive calculations and analyses on the suspended spans of offshore pipelines under different geological conditions in response to complex routing situations. They have successfully solved world-class submarine pipeline engineering technical problems such as ultra long and ultra high suspended spans, and have made adaptive modifications to the key equipment of the main operating vessel "Offshore Oil 201", We have independently developed the first fully automatic welding equipment process for large diameter and thick wall offshore pipelines in China, achieving more than 10 technological breakthroughs. During construction, we have set a record for the laying speed of domestic 20 inch deep-water pipelines of 2.65 kilometers per day.
It is understood that up to now, China has laid over 9000 kilometers of offshore oil and gas pipelines, which is equivalent to the distance of the Shanghai Paris route.
(Image provided by CNOOC)
Disclaimer: The content of this article is sourced from the internet. The copyright of the text, images, and other materials belongs to the original author. The platform reprints the materials for the purpose of conveying more information. The content of the article is for reference and learning only, and should not be used for commercial purposes. If it infringes on your legitimate rights and interests, please contact us promptly and we will handle it as soon as possible! We respect copyright and are committed to protecting it. Thank you for sharing.(Email:[email protected])
Mobile advertising space rental |
Tag: and The longest deepwater oil gas pipeline in China
Indonesia's Yawan High Speed Rail Joint Debugging and Trial Speed Reaches 350 kilometers per hour
NextWhat is the Difficulty in Mass Production of Solid-state battery
Guess you like
- Detail
- Detail
-
Ant Group Powers the Greater Bay Area's "One-Hour Living Circle" and Fuels Global "ChinaTravel Boom"Detail
2024-11-21 19:23:04 1
-
Shenzhen's First Roadside Supercharger Station Commences Trial Operation, Ushering in a New Era for the "Supercharging City"Detail
2024-11-21 11:25:06 1
-
Xiaomi's High-End Strategy: An In-Depth Analysis of Q3 2024 Financial Results and Future OutlookDetail
2024-11-19 23:07:40 1
-
TSMC's Sudden Shift: A Global Chip Giant's Difficult Choices in the US-China GameDetail
2024-11-19 12:27:48 1
-
International Space Station Leak Crisis: NASA's Emergency Evacuation Plan and Signals of Chinese CooperationDetail
2024-11-19 11:34:51 1
-
Ten Years of Searching: Li Eryou's Unwavering Hope in the Search for His Son on MH370Detail
2024-11-18 18:39:16 1
-
The Facial Swelling of Shenzhou 18 Astronauts: The Physiological Cost of Space Exploration and Future ChallengesDetail
2024-11-17 08:03:04 11
-
Xiaomi Automobile Unveils Intelligent Chassis Pre-Research Technology, Ushering in a New Era of "Human-Car-Home Full Ecosystem"Detail
2024-11-14 11:24:27 1
-
Douyin E-commerce Double 11 Data Report: Merchants Businesses Grow, Consumer Trends EmergeDetail
2024-11-14 11:23:11 1
-
New Trends in SOE Reform: Focusing on Five Values to Build a "Living Organism"Detail
2024-11-14 11:19:26 1
-
CATL Chairman Zeng Yuqun: Musk Doesn't Understand Batteries, Tesla's Bet on Cylindrical Batteries is Doomed to FailDetail
2024-11-13 18:47:38 11
-
China Eastern Airlines Technology and Thales Renew Cooperation Agreement, Deepening Avionics Maintenance PartnershipDetail
2024-11-13 16:40:50 1
- Detail
- Detail
- Detail
-
Li Jiaqi's Livestream Double 11 Report: Domestic Brands Surge, Winter Warmer Economy BoomsDetail
2024-11-12 11:07:26 11
-
BYD: Plug-in Hybrids "To the Rescue," Behind the Price War Lies a "Davis Double-Click" in ProfitabilityDetail
2024-11-12 10:49:05 1
-
The Rise of Online Livestreamers: A Mass Career with 15 Million Dream Chasers in Live RoomsDetail
2024-11-11 15:27:33 11